How Long Does It Take to Build a Website?

Realistic website build timelines for New Zealand businesses, broken down by site type and project phase, plus the things that most often cause delays.

By Spiro Kovac · · 8 min read

On this page
  1. Website build timelines by type of site
  2. The phases of a website build
  3. How long does an e-commerce website take?
  4. What delays website projects (and how to avoid it)
  5. Is it worth building a website faster?
  6. How long does it take to build a website yourself?
  7. What affects the cost alongside the timeline
  8. A realistic launch plan

How long it takes to build a website depends mostly on the type of site and how quickly content and feedback arrive. As a guide for New Zealand businesses, a typical custom business website takes 1 to 4 weeks from kick-off to launch, and an e-commerce or larger site takes 5 to 12 weeks. A simple landing page can be done in days. The design and build work itself is rarely the bottleneck; waiting on copy, photos and approvals usually is.

This guide breaks down timelines by site type, walks through each phase of a build, and covers the delays we see most often, so you can plan a launch date you will actually hit.

Website build timelines by type of site

Type of websiteTypical timelineWhat drives the time
Single landing pageA few days to 1 weekOffer clarity, copy, tracking setup
Small business site (5 to 10 pages)1 to 2 weeksContent readiness, feedback speed
Custom business site (10 to 25 pages, service and location pages)2 to 4 weeksCopywriting, photography, number of page templates
Website redesign with SEO migration2 to 5 weeksNumber of existing URLs, redirect mapping, content rewrite
E-commerce store (Shopify or WooCommerce)5 to 8 weeksProduct data, payments, shipping rules, integrations
Larger store or complex site8 to 12 weeksData migration, custom functionality, multiple stakeholders

These are calendar timelines from kick-off to launch, not hours of work. A site that takes 15 working days of effort can easily stretch to two months if each feedback round takes a week. The reverse is true too: a business that arrives with content ready and one decision maker can be live much faster than they expect.

The phases of a website build

Every agency labels these a bit differently, but a well-run project moves through the same stages. Here is how a typical 2 to 4 week custom build breaks down. You can see how we run ours on our web design process page.

  1. Discovery and planning (2 to 4 days)

    Agree goals, audience, services and areas to target. Do keyword research, map out the sitemap and decide what each page needs to achieve. This is where SEO structure is set, and it saves days of rework later.

  2. Content and wireframes (3 to 7 days)

    Page layouts are sketched and copy is written or collected. If you are supplying your own content, this is the phase most likely to stall.

  3. Design (3 to 5 days)

    The visual design is created for the homepage and key templates, usually desktop and mobile, then refined through one or two feedback rounds.

  4. Build and integrations (4 to 10 days)

    The site is developed in its CMS, with forms, tracking, Google Business Profile links, schema markup and any booking or payment tools connected.

  5. Testing and launch (2 to 3 days)

    Check speed, mobile layouts, forms, redirects and analytics, then go live and submit the sitemap to Google Search Console.

Some of these phases overlap. Design can start on the homepage while copy for inner pages is still being written, which is one of the easiest ways to shorten a project without cutting corners.

How long does an e-commerce website take?

Online stores take longer because there is more to set up and more that can go wrong at checkout. On top of the normal design and build phases, an e-commerce project needs:

  • Product data loaded or migrated, including variants, images, descriptions and stock levels.
  • A payment gateway such as Stripe or Windcave configured and tested, with any buy now, pay later options you want.
  • Shipping rules for NZ Post or your courier, including rural delivery and any international zones.
  • Prices displayed GST-inclusive to consumers, with tax settings that match your accounting.
  • Policy pages for returns, refunds and delivery.
  • Integrations with inventory, accounting or email marketing tools.

A store with 30 products and simple shipping might launch in 5 or 6 weeks. A store migrating 2,000 products from an old platform, with custom filtering and an ERP integration, can take 12 weeks or more. If you are weighing platforms, our WordPress vs Shopify vs Webflow comparison covers how each affects build time, and our e-commerce website design service explains what is included.

What delays website projects (and how to avoid it)

Almost every late project we have seen comes down to one of a handful of causes. Very few are technical.

1. Content is not ready

Copy, photos, team bios, product details and testimonials are the number one source of delay. Writing ten pages of good copy is real work, and it tends to slip behind day-to-day business. Either start writing before kick-off or have your web designer write it for you.

2. Slow or scattered feedback

If each feedback round takes a week, a project with four rounds loses a month. Feedback that arrives from three people with conflicting opinions is even slower. Nominate one decision maker and book feedback time in your calendar as soon as the timeline is agreed.

3. Scope creep

New features added mid-project, such as a booking system, a members area or another ten pages, push the launch date out. Good ideas that arrive late can usually go into phase two after launch.

4. Waiting on third parties

Domain logins held by a previous developer, DNS access through an IT provider, payment gateway approvals and booking software accounts all take time to sort out. Find your logins early. If you are unsure who controls your domain, our guide to .co.nz vs .nz vs .com domains explains how NZ domain registration works.

5. Photography

Real photos of your team, premises and work make a huge difference to trust, but a photo shoot needs booking, good weather for outdoor work and time for editing. Book it in week one, or launch with your best existing photos and swap them later.

6. Unclear goals

Projects that start with "we just need a new website" often pause halfway while the business works out what it actually wants. Spend an hour before kick-off writing down your main services, target areas, ideal customer and what a successful enquiry looks like.

Fastest route to launch: have your logo files, domain login, a list of services and at least rough page notes ready before kick-off, and agree one person who gives feedback within 48 hours. That alone can take a week or more off a typical build.

Is it worth building a website faster?

Speed is good. Rushing is not. The phases that get squeezed when a deadline is tight are planning and testing, and those are exactly the ones that decide whether the site ranks and converts.

A site launched in five days with no keyword research, no location pages and broken form tracking will look finished, but it will not bring in work. On a redesign, skipping the SEO migration can wipe out years of rankings overnight. Our website redesign SEO checklist covers the steps that should never be skipped, however tight the timeline, and every website redesign we take on includes 301 redirects and a full migration check as standard.

If you have a hard deadline, such as a product launch, an Ads campaign or a trade show, tell your designer at the start. A launch-critical version of the site can often go live on time, with secondary pages and extras following a week or two later.

How long does it take to build a website yourself?

With a DIY builder like Wix or Squarespace, a confident owner can put up a basic site in a weekend or two. The catch is that the time is spread across learning the tool, writing copy, sourcing images and fiddling with layouts, usually in the evenings. Many business owners find a DIY site takes months of on-and-off work to finish properly.

DIY sites also tend to miss the parts that take expertise rather than time: page speed, site structure, local SEO and conversion tracking. We regularly fix Wix and Squarespace sites that look fine but do not appear in Google for the services the business actually sells.

What affects the cost alongside the timeline

Time and cost are linked, but not perfectly. A longer project is not always more expensive, because delays caused by waiting on content do not add design hours. What does add cost is extra page templates, custom functionality, copywriting, product loading and integrations.

Every project with our web design company in Auckland is quoted at a fixed price with an agreed timeline before work starts, so you know both numbers up front. Most custom small business sites fall between $3,500 and $8,000 +GST, and e-commerce or larger sites start from about $8,000. You can see typical ranges on our website pricing page or read the full website design cost guide for NZ.

A realistic launch plan

If you are starting from scratch today, a sensible plan for a typical service business looks like this:

  • Week 0: gather logins, logo, brand colours, a services list and target areas.
  • Week 1: discovery, sitemap, wireframes and copy underway.
  • Week 2: design approved, build begins, photos taken.
  • Week 3: build complete, content loaded, testing and fixes.
  • Week 4: launch, sitemap submitted, Google Business Profile updated and tracking checked.

Plenty of projects finish well inside that window. The ones that run over almost always do so for reasons the business can control, which is good news, because it means the timeline is largely in your hands.

Frequently asked questions

Can a website be built in a week?

A small, well-scoped business site can go from kick-off to launch in about a week if the content, photos and logo are ready on day one and feedback comes back within a day. Most projects take a little longer because content is still being written. A rushed build that skips planning usually costs more time later in rework.

How long does a Shopify or e-commerce website take to build?

Most e-commerce builds take 5 to 12 weeks. The range depends on how many products need loading, whether data is migrating from an old store, the payment gateway and shipping setup, and integrations such as inventory or accounting software. Product photos and descriptions are the most common cause of delays.

What slows down a website project the most?

Content. Waiting on page copy, photos, product details or sign-off from several decision makers delays more projects than design or development ever does. Slow feedback rounds are a close second. Agreeing who approves what and booking feedback time in advance keeps most projects on schedule.

How long does a website redesign take?

A redesign of a typical business site usually takes a similar time to a new build, roughly 1 to 4 weeks, plus time for the SEO migration. That means mapping old URLs, setting up 301 redirects and checking rankings after launch. Larger sites with hundreds of pages or a store take longer.

How long after launch will my website show up on Google?

Google usually finds and indexes a new site within days to a few weeks, especially once you submit a sitemap in Search Console. Ranking well for competitive searches takes longer, often several months, and depends on your content, local signals, reviews and links. A redesign that keeps redirects in place should hold existing rankings.

The customers are out there. Let's make them ring your phone.

Tell us about your business and we'll come back within one working day with ideas, a timeline and a fixed-price quote. No obligation, no jargon.

Free 20-minute website plan · Real numbers · No obligation